Process Water Surface Impoundment
Gets Major Improvements
Sump & Drain Pipe
Pump Station
Subgrade
Vent System
Drain Pipe
Manhole
Liner
Extents
Feed
Pipe
The client, a large producer of fertilizer products, has a process water impoundment at their chemical processing facility that has been in operation for years. The renewal of their discharge permit stipulated that the impoundment needed to implement a geosynthetic liner system. The client also had some operational challenges due to the age of the impoundment that did not allow them to use the asset to its full potential. Therefore, the client decided to take advantage of the situation and incorporate major upgrades to the impoundment while implementing a geosynthetic liner system. Services provided for this project include:
-
Liner system design
-
Impoundment grading plans
-
Subgrade vent system layout and design
-
Impoundment sump and new HDPE drain pipe design and details
-
HDPE-lined precast concrete drain pipe manhole design and details
-
Permitting and plan approval by state regulatory agency
-
Development of the construction quality assurance (CQA) plan
-
CQA oversight and certification
Construction is planned for summer 2019.